← Pinterest Interview Insights

Pinterest·Machine Learning Engineer·Technical Phone Screen·Senior

Senior
May 2026

Summary

Pinterest MLE interview with a classic scheduling/optimization problem. Nothing too surprising but the pruning details matter more than you'd think.

Questions Asked (1)

Q1

Given an array of job durations and k workers, assign every job to exactly one worker so that the maximum total working time across all workers is minimized. Return that minimum possible maximum.

Algorithms & Data StructuresTechnical Trade-offs
Author's notes

I went with backtracking first and got it mostly right, but the pruning is where things get tricky.

Create a free account to read the full note

AI HintsAI Generated

Suggested Approach

This is a classic load balancing problem that can be solved using binary search on the answer combined with a greedy feasibility check. The key is to recognize that the minimum possible maximum load lies between the maximum job duration and the sum of all job durations, and then binary search for the smallest value for which a valid assignment exists.

Pro tip: Always clarify that jobs are indivisible and each worker's load is the sum of assigned job durations. Mention that while the problem is NP-hard in general, the binary search + greedy approach works because we only need to minimize the maximum, not find an exact partition.

1. Understand the problem and constraints

Restate the problem: assign each job to exactly one worker, minimize the maximum total working time. Identify that jobs are indivisible and workers can take any number of jobs.

2. Define search space and feasibility check

The answer lies between max(job_durations) and sum(job_durations). For a given candidate maximum load, check if it's possible to assign jobs to at most k workers without exceeding that load using a greedy algorithm.

3. Implement binary search

Binary search over the range [max, sum] to find the smallest feasible maximum load. At each step, run the greedy feasibility check and adjust the bounds accordingly.

4. Analyze complexity and trade-offs

Time complexity is O(n log(sum - max)) where n is number of jobs. Space complexity is O(1). Discuss that this is optimal for this problem and mention alternative approaches like DP or heuristics if k is small.

5. Test with edge cases

Consider cases like k >= n (each job to a worker), k = 1 (all jobs to one worker), and jobs with large durations. Verify the solution handles these correctly.

Key Points to Mention

  • Binary search on the answer (minimax problem)
  • Greedy feasibility check: assign jobs to workers, starting a new worker when current load would exceed the candidate maximum
  • Lower bound = max(job_durations), upper bound = sum(job_durations)
  • Time complexity O(n log(sum)) and space O(1)
  • The problem is equivalent to multiprocessor scheduling, which is NP-hard for exact minimization, but binary search + greedy works for this variant
  • Edge cases: k >= n, k = 1, and zero-duration jobs

AI-generated suggestions, not part of the candidate's original notes. May be inaccurate — verify before relying on them.