Amazon SWE interview with a greedy scheduling problem that had a bunch of follow-ups stacked on top of each other. The core question wasn't too bad but the variants kept coming and I wasn't fully prepared for all of them.

Questions Asked (4)

Q1

You have a daily task limit, a list of required tasks per day, and a shared pool of optional tasks. Each day you must complete its required task, and if time allows you can schedule at most one optional task from the pool (each optional used at most once). How do you maximize the number of optional tasks scheduled, and how do you reconstruct a valid assignment?

Algorithms & Data StructuresTechnical Trade-offs
Author's notes

This is a greedy problem.

Create a free account to read the full note

AI HintsAI Generated

Suggested Approach

Model the problem as a bipartite matching between days and optional tasks, where an edge exists if the optional task can be scheduled on that day (i.e., the day's required task plus the optional task fit within the daily limit). Use a greedy algorithm with a priority queue to maximize the number of optional tasks scheduled, and then reconstruct the assignment by backtracking through the matching decisions.

Pro tip: Emphasize that the greedy approach works because of the matroid structure of the constraints, and mention that you can also use a max-flow formulation for clarity. This shows depth and awareness of alternative solutions.

1. Understand the constraints and objective

Clarify that each day has a required task consuming some time, and we can add at most one optional task if the total time does not exceed the daily limit. The goal is to maximize the number of optional tasks scheduled, each used at most once.

2. Model as a matching problem

Create a bipartite graph with days on one side and optional tasks on the other. Add an edge if the optional task can be scheduled on that day (i.e., required_time + optional_time <= daily_limit). The problem reduces to finding a maximum matching.

3. Choose an efficient algorithm

Use a greedy algorithm: sort days by their remaining capacity (daily_limit - required_time) in ascending order, and for each day, assign the optional task with the smallest duration that fits. Alternatively, use Hopcroft-Karp for O(E√V) or a max-flow formulation.

4. Reconstruct the assignment

During the greedy assignment, keep track of which optional task is assigned to which day. If using matching algorithms, augment the matching and store the pairs. Finally, output the list of (day, optional_task) pairs.

5. Analyze complexity and trade-offs

Discuss time and space complexity: greedy with sorting and priority queue is O((D + O) log O) where D is number of days and O is number of optional tasks. Mention that max-flow is O(V^2 E) but simpler to reason about.

Key Points to Mention

  • Bipartite matching formulation between days and optional tasks
  • Greedy strategy: process days by increasing remaining capacity and assign smallest fitting optional task
  • Use of priority queue or balanced BST to efficiently find the smallest fitting task
  • Reconstruction by storing parent pointers or assignment array during matching
  • Complexity analysis: O((D + O) log O) for greedy, O(E√V) for Hopcroft-Karp
  • Trade-offs: greedy is simpler and faster, but max-flow is more general and easier to prove correctness

AI-generated suggestions, not part of the candidate's original notes. May be inaccurate — verify before relying on them.

Q2

How would your approach change if each optional task could only be scheduled on its corresponding day, meaning optional[i] is only eligible for day i?

Algorithms & Data Structures
Author's notes

Simpler actually.

Create a free account to read the full note

AI HintsAI Generated

Suggested Approach

First, clarify the original problem and the constraint change: each optional task is tied to a specific day, so you can only choose to do it on that day or skip it. Then, explain how this transforms the problem from a flexible scheduling or selection problem into a per-day decision problem, likely simplifying the algorithm to a greedy or dynamic programming approach that processes days sequentially.

Pro tip: Emphasize that the constraint removes cross-day dependencies, which often allows for a simpler greedy solution—but always verify with edge cases like overlapping mandatory tasks or negative profits. Mention that you'd discuss trade-offs between greedy and DP with the interviewer before coding.

1. Restate the problem and new constraint

Confirm your understanding: optional[i] can only be scheduled on day i, so you must decide for each day whether to take that optional task or not, while respecting mandatory tasks and other constraints.

2. Identify the impact on the original solution

Explain how the original approach (e.g., sorting by profit, DP over days, or greedy selection) changes: the decision for each optional task becomes local to its day, eliminating the need to consider moving tasks across days.

3. Propose a revised algorithm

Describe a step-by-step method: iterate through days, for each day check if the optional task can be done given mandatory tasks and capacity, and decide based on profit or other criteria. If multiple optionals per day, choose the best; if only one, it's a binary choice.

4. Analyze complexity and edge cases

State the time and space complexity of the new approach (likely O(n) or O(n log n) if sorting is needed) and discuss edge cases: days with no optional task, optional task conflicting with mandatory, negative profit, etc.

5. Compare with original and conclude

Summarize how the constraint simplifies the problem and why the new approach is correct. If applicable, mention that the original problem might have been NP-hard or required complex DP, but this version is tractable.

Key Points to Mention

  • The constraint makes each optional task day-specific, removing cross-day scheduling flexibility.
  • This often reduces the problem to a per-day greedy choice or a simple linear DP.
  • Consider mandatory tasks and capacity constraints that might prevent taking the optional task.
  • Edge cases: optional task with negative profit, multiple optionals on same day (if allowed), or no optional task.
  • Time complexity improvement: from potentially O(n^2) or exponential to O(n) or O(n log n).
  • Correctness argument: since decisions are independent across days, local optimal choices lead to global optimum (if greedy applies).

AI-generated suggestions, not part of the candidate's original notes. May be inaccurate — verify before relying on them.

Q3

What happens when some required tasks exceed the daily limit? How do you handle that edge case?

Algorithms & Data StructuresTechnical Trade-offs
Author's notes

I blanked for a second.

Create a free account to read the full note

AI HintsAI Generated

Suggested Approach

Clarify the problem constraints first, then propose a solution that handles the edge case by either redistributing tasks, prioritizing, or extending the time window. Discuss trade-offs between correctness, efficiency, and real-world constraints, and mention how you would test and monitor the solution.

Pro tip: At Amazon, emphasize customer impact and operational excellence: explain how your solution ensures no task is dropped and how you would instrument metrics to detect and alert on such edge cases.

1. Clarify the problem

Ask questions to understand the exact constraints: what is the daily limit, what defines a 'required' task, and what are the consequences of exceeding it?

2. Identify possible strategies

Brainstorm approaches such as prioritizing tasks, batching, deferring non-critical tasks, or dynamically adjusting the limit based on load.

3. Evaluate trade-offs

Compare strategies on correctness, latency, resource usage, and business impact. Consider edge cases like multiple days of overflow or dependencies between tasks.

4. Propose a robust solution

Select the best approach, describe the algorithm or system design, and explain how it handles the edge case without violating constraints.

5. Discuss testing and monitoring

Outline unit tests, integration tests, and production monitoring to ensure the solution works and to detect failures early.

Key Points to Mention

  • Prioritization of tasks based on criticality or deadlines
  • Dynamic adjustment of limits or quotas
  • Queueing and backpressure mechanisms
  • Trade-offs between consistency and availability (CAP theorem)
  • Amazon leadership principles like Customer Obsession and Ownership
  • Metrics and alarms for proactive detection

AI-generated suggestions, not part of the candidate's original notes. May be inaccurate — verify before relying on them.

Q4

How would you generalize the solution if each day could accommodate up to k optional tasks instead of just one?

Algorithms & Data StructuresTechnical Trade-offs
Author's notes

The greedy still works but now you're pulling up to k tasks per day from the sorted pool.

Create a free account to read the full note

AI HintsAI Generated

Suggested Approach

First, clarify the problem and constraints, then propose a dynamic programming solution that generalizes the original recurrence to allow up to k tasks per day. Discuss the time and space complexity, and consider optimizations such as using a monotonic queue or segment tree to achieve O(nk) or O(n log n) time.

Pro tip: Demonstrate awareness of trade-offs: for small k, a simple DP is fine, but for large k, you might need a more efficient data structure. Also, mention that the problem can be modeled as a shortest path or min-cost flow for additional insight.

1. Clarify the problem

Restate the problem to ensure understanding: each day can accommodate up to k optional tasks, and we need to generalize the solution. Ask about constraints on n (number of days) and k, and whether tasks have dependencies or weights.

2. Define DP state and recurrence

Define dp[i][j] as the optimal value up to day i with j tasks completed (or similar). The recurrence considers taking 0 to k tasks on day i, leading to a transition that sums over previous states.

3. Analyze complexity and optimize

Naive DP takes O(n * k * m) where m is the number of tasks per day. Optimize using prefix sums, monotonic queue, or segment tree to reduce to O(nk) or O(n log n).

4. Discuss trade-offs and alternatives

Compare DP with greedy or flow-based approaches. Mention that for large k, a greedy might not work, but DP with optimization is robust. Also, consider space optimization if only previous day's states are needed.

5. Test with examples and edge cases

Walk through a small example to validate the recurrence. Consider edge cases like k=0, k > number of tasks, or n=1.

Key Points to Mention

  • Dynamic programming state definition and transition
  • Time and space complexity analysis
  • Optimization techniques (monotonic queue, segment tree, prefix sums)
  • Trade-offs between different approaches (DP vs greedy vs flow)
  • Handling constraints and edge cases
  • Potential for space optimization (rolling array)

AI-generated suggestions, not part of the candidate's original notes. May be inaccurate — verify before relying on them.